How to Install Vertical Turbine Pumps in Deep Wells
news

How to Install Vertical Turbine Pumps in Deep Wells

2025-11-14
Share :

Vertical turbine pumps (VTPs) remain the most reliable solution for water supply in deep wells, underground tanks, and applications where the water source is below ground level. In the fire protection industry, they play a critical role in ensuring a stable, high-flow water supply, especially where surface or municipal water supplies are insufficient.

However, the performance and lifespan of a vertical turbine pump depend heavily on proper installation. Errors made during installation—such as misalignment, improper lubrication, or incorrect column assembly—can lead to vibration, low efficiency, premature wear, or even catastrophic failure.

This article provides a comprehensive, professional guide to installing vertical turbine pumps in deep wells, suitable for contractors, system designers, and engineering teams involved in fire protection projects.


1. Understanding Vertical Turbine Pumps for Deep Wells

A vertical turbine pump typically consists of these major components:

  • Pump head / discharge head

  • Vertical hollow shaft motor or right-angle gear drive

  • Line shaft and shaft sleeves

  • Column pipes

  • Bowl assembly (multiple stages)

  • Strainer

In deep wells, the pump bowl assembly is submerged in water, and the column system transfers water upward to the pump head. Because of the vertical structure and depth requirements, installation must be precise, step-by-step, and compliant with NFPA 20 when used for fire protection.


2. Pre-Installation Preparation

Before any physical installation begins, proper planning ensures smooth workflow and minimizes mistakes.

2.1 Verify the Water Source

  • Confirm depth to water surface and total well depth.

  • Ensure water level supports the pump's minimum submergence requirements.

  • Measure straightness and diameter of the well casing to prevent interference during lowering.

2.2 Foundation and Base Plate Preparation

The foundation must be:

  • Smooth, level, and strong enough to support the pump and motor weight.

  • Large enough for bolt positioning and maintenance clearance.

  • Free from cracks or settlement issues.

Anchor bolts must be properly positioned based on the discharge head dimensions.

2.3 Check All Components Before Installation

Inspect components for:

  • Physical damages

  • Corrosion

  • Smooth thread engagement on column pipes

  • Straightness of shafts

  • Clean bearing surfaces

Any damaged part must be replaced before lowering into a deep well, as retrieval is difficult.


3. Step-By-Step Installation Procedure

3.1 Install the Discharge Head

The discharge head supports the motor or gear drive and connects the column pipe to the system discharge.

Steps:

  1. Place the discharge head on the prepared foundation.

  2. Use a spirit level to ensure accurate leveling.

  3. Tighten anchor bolts gradually in a cross pattern.

  4. Double-check alignment before proceeding.

A level discharge head is critical to maintaining vertical alignment of the entire pump string.


3.2 Assemble and Lower the Pump Bowl Assembly

The bowl assembly is the heart of the vertical turbine pump. For deep wells, this assembly is lowered first.

Procedure:

  1. Attach lifting equipment to the bowl assembly using manufacturer-approved lifting points.

  2. Carefully lower the bowl unit into the well casing.

  3. Maintain vertical alignment to avoid casing wall contact.

  4. Ensure the first shaft section is correctly attached.


3.3 Install Column Pipes and Line Shaft Assembly

The column installation is done in sections, especially in deep wells of 30 meters or more.

Each section involves:

3.3.1 Connecting Column Pipes

  • Apply pipe thread lubricant or sealing compound.

  • Tighten connections securely.

  • Verify the straightness of each section.

3.3.2 Installing Line Shaft and Bearings

Inside each column pipe is the line shaft.
Procedures:

  1. Install line shaft, shaft sleeves, and bearings according to manufacturer instructions.

  2. Check that bearings are properly lubricated:

    • Water-lubricated bearings for fire pumps

    • Oil-lubricated systems if specified

  3. Measure shaft end play and adjust as needed.

  4. Lower the column section and connect it with the previous one.

Repeat these steps for every section until the final column reaches the discharge head.


3.4 Maintain Proper Shaft Alignment

Vertical alignment is essential for ensuring smooth operation without vibration.

During installation:

  • Check run-out of the shaft using a dial indicator.

  • Adjust using shims at the foundation base if needed.

  • Ensure alignment is maintained through all column sections.

Even slight misalignment can cause:

  • Excessive vibration

  • Bearing wear

  • Overheating

  • Reduced pump efficiency


3.5 Install the Discharge Head Shaft and Motor

Once the column assembly reaches the surface:

3.5.1 Final Shaft Coupling

  • Connect the head shaft to the motor shaft or right-angle gear drive.

  • Verify coupling tolerances.

  • Adjust vertical spacing to meet required pump head lift and thrust.

3.5.2 Install the Electric Motor or Diesel Engine Gear Drive

For fire pump applications:

  • Vertical hollow shaft motor is common.

  • Diesel engine with right-angle gear drive is used where electric power is unreliable.

Ensure:

  • Motor base matches the discharge head.

  • Thrust bearing capacity meets pump design requirements.

  • Electrical connection follows safety and fire protection codes.


4. Well Development and Pre-Startup Cleaning

Before operating the pump:

  • Clean the well of silt, sand, and debris.

  • Ensure the water source meets pump NPSH requirements.

  • Flush the system to remove contaminants.

This step protects the bowl assembly and bearings during initial startup.


5. Final Alignment and Start-Up Procedures

5.1 Mechanical Alignment

Perform a complete alignment verification:

  • Check shaft straightness

  • Verify coupling spacing

  • Measure vibration baseline

  • Tighten all structural bolts

5.2 Electrical and Control Checks

Include:

  • Motor insulation resistance tests

  • Starter and controller checks

  • Rotation direction verification (brief jog only)

Rotation must match the manufacturer's direction arrow.

5.3 Initial Startup

During the first run:

  • Monitor vibration

  • Check for abnormal noises

  • Observe pressure gauge and flow meter

  • Confirm rated flow and head performance

  • Inspect temperature at bearings

If any abnormality occurs, shut down and investigate immediately.


6. NFPA 20 Considerations for Fire Pump Installations

Vertical turbine pumps used for fire protection must follow NFPA 20 requirements:

  • Pump must provide rated flow at rated pressure.

  • Minimum submergence must be maintained at all times.

  • Water supply must be reliable and stable.

  • Controllers must be UL-listed and sized correctly.

  • The installation must allow for easy inspection and maintenance.

NFPA 20 also requires that the pump be tested at full flow and churn conditions after installation.


7. Common Installation Mistakes to Avoid

7.1 Improper Shaft Lubrication

Can cause bearing failure during initial operation.

7.2 Inadequate Alignment

Leads to vibration and shortens pump life.

7.3 Insufficient Water Submergence

Causes vortexing, cavitation, and reduced performance.

7.4 Loose Connections in Column Pipes

A serious problem that can cause the pump to drop or misalign inside the well.

7.5 Incorrect Motor Rotation

Can severely damage the pump in seconds.

Awareness of these issues ensures safe, reliable installation.


8. Maintenance Recommendations After Installation

Proper maintenance keeps the pump performing at top efficiency.

  • Conduct regular vibration analysis.

  • Inspect shaft sleeves and bearings periodically.

  • Test pump performance every year or based on local fire regulations.

  • Check water level seasonally, especially in deep wells.

  • Re-align the motor after any major maintenance.

A well-installed and well-maintained vertical turbine pump can operate efficiently for decades.


Conclusion

Installing a vertical turbine pump in a deep well requires precision, technical expertise, and strict compliance with fire safety standards. Every step—from pre-installation planning, foundation preparation, column pipe assembly, shaft alignment, to final performance testing—directly influences the pump’s long-term reliability.

For fire protection systems, the installation must always meet NFPA 20 requirements to ensure reliable water delivery during emergencies. By following the guidelines in this article, contractors and engineers can achieve stable, efficient, and long-lasting vertical turbine pump performance in deep well applications.

If you need a professional consultation or customized vertical turbine fire pump solution, you can always reach out for expert assistance.

Get in touch with us
Rellene Su Consulta Y Nos Pondremos En Contacto Con Usted Las 24 Horas.
X
Get in touch with us
For Jiuyi Fire Technology Co., Ltd future focus on oversea market product, like the EDJ fire pump set, EJ, DJ, EEJ and so on, also include the vertica